IEEE P802.11 - TASK GROUP M - MEETING
UPDATE:
Status of Project IEEE 802.11m
March 2008
Task Group m (TGm) met in Orlando at the Caribe-Royal Resort. The task group held one meeting and focused on completing the response to a interpretation request Transmit Power Control (TPC) in reference to EIRP in reference to P802.11-2007 Clause 7.3.2.18.
TBm completed and approved of the items in the interpretation request and created doc: 08/0375r0 as the approved response by the working group.
The relavent documents for this session were: 08/0390r0, 08/391r0, and 08/375r0.
Goals for May 2008
1) Process any new incoming interpretation requests
2) Begin outlining requirements for the next revision of the P802.11 standard (including TGr, TGk, TGn) for target completion by 2011
January 2008
Task Group m (Tgm) did not meet at the January interim session in Taipei, Taiwan. TGMb will resume meeting at the March 2008 plenary session in Orlando, Florida. The tentative goals for the group at the March 2008 session are as follows:
Goals for March 2008
1) Complete interpretation request on the subject of TPC (transmit power control) in Clause 7.3.2.18
2) Process request on the usage of "shall" in Clause 10.0
3) Process any new interpretations requests from the IEEE
November 2007
Task Group m (Tgm) met in Atlanta at the Hyatt Regency. The task group held one meeting and focused on completing the response to a interpretation request on TCLAS Element from 802.11e-2005 in doc: 07/2248r0. Tgmb completed and approved of the items in the interpretation request and created doc: 07/2248r1.
The relavent documents for this session were: 07/2248r1, 07/2922r0, and 07/2920r0.
Goals for January 2008
1) Process interpretation request on the subject of TPC (transmit power control) in Clause 7.3.2.18
September 2007
Task Group m (Tgm) did not meet at the September interim session in Hawaii. TGMb will resume meeting at the November 2007 plenary session in Atlanta, GA. The tentative goals for the group at the November 2007 session are as follows:
Goals for November 2007
1) Complete interpretation response on TCLAS Element held over from July 2007
2) Process interpretation request on the subject of TPC (transmit power control) in Clause 7.3.2.18
3) Process request on the usage of "shall" in Clause 10.0
July 2007
Task Group m (Tgm) met in San Francisco at the Hyatt Regency. The task group held two meetings and focused on responding to a interpretation request on TCLAS Element from 802.11e-2005. Tgm complete 50% of the items in the interpretation request. The relavent documents for this session were: 07/2248r0, 07-2151r0, and 07/2251.
Goals for September 2007
1) Complete interpretation response on TCLAS Element
May 2007
The task group finished its work as TGma the January 2007 session. Task Group m (Tgm) met in Montreal, Canada as
TGmb. The task group held two meetings and focus on gathering unresolved comments from the 802.11REV-ma sponsor ballot that were considered "out-of-scope" of the standard. In addition the task group started gathering interpretation requests that resolved around channel numbering. The task group produced a document that combined the comments and requests that will be resovled at the next 802.11 session in July 2007.
Goals for July 2007
1) Begin work on resolving (out-of-scope) comments from 802.11REV-maD9.0
2) Resolve interpretation requests from January 2007
January 2007
Task Group m met in
London, UK. The task group considered a request for interpretation of the
standard on the subject of an indecipherable sentence in clause 17. The
task group produced a response that was approved by the 802.11 working group.
The task group also produced a proposal for a PAR for further maintenance of
the standard. This was also approved by the working group and forwarded
for the consideration of the 802 Executive Committee.
Unless the consideration of the 802.11REV-ma draft by the IEEE-SA Standards
Board Review committee does not go well, this is the last report of TGma, as
it will be dissolved upon approval of that draft by the IEEE-SA Standards
Board.
November 2006
Task Group m met in
Dallas, TX. The result of the fourth sponsor
recirculation ballot on 802.11REV-ma that concluded shortly before the
November 2006 session was successful, meeting the requirements of the LMSC
Executive Committee for conditional forwarding to RevCom.
The editor will produce a clean draft that accepts the marked changes.
The draft and the results of the sponsor balloting process will be submitted
to RevCom for their Early Consideration agenda that begins after their meeting
in December.
The task group also responded to one interpretation request
submitted on the subject of the replay protection mechanism used by the TKIP
cipher suite.
The goals for the
January 2007 session are:
September 2006
Task Group m met in
Melbourne, Victoria, Australia to process the comments received from the third sponsor
recirculation ballot that concluded shortly before the September 2006 session.
The recirculation ballot resulted in 41 comments to be addressed. The task
group responded to all of the comments. The working group
approved the comment resolutions. The editor was directed to produce an
updated draft.
A third sponsor recirculation ballot will begin shortly after the close of the
session.
The task group also responded to two interpretation requests
submitted on the subjects of unknown values in a received information element
and conflict between clause 9 and annex C on the use of rery counters.
The goals for the
November 2006 session are:
-
•Process
comments received from fourth sponsor recirculation ballot, if necessary
-
•Submit report to 802 EC for forwarding to RevCom
-
•Process any interpretation requests received
July 2006
Task Group m met in
San Diego, California to process the comments received from the second sponsor
recirculation ballot that concluded immediately before the July 2006 session.
The recirculation ballot resulted in 90 comments to be addressed. The task
group responded to all of the comments. The working group
approved the comment resolutions.
A third sponsor recirculation ballot will begin shortly after the close of the
session.
The task group also responded to an interpretation request
submitted on the subject of RTS/CTS usage during interrupted fragment bursts.
The goals for the
September 2006 session are:
- Process the comments received from the third sponsor recirculation ballot
- Create a new draft and send it to a fourth sponsor recirculation ballot,
if necessary
- Forward the draft to RevCom for approval, if possible
- Process any interpretation requests received
May 2006
Task Group m met in
Jacksonville, Florida to process the comments received from the first sponsor
recirculation ballot that concluded immediately before the May 2006 session.
The recirculation ballot resulted in 156 comments to be addressed. The task
group responded to all of the comments. The working group
approved the comment resolutions.
A second sponsor recirculation ballot will begin shortly after the close of the
session.
The goals for the
July 2006 session are:
- Process the comments received from the second sponsor recirculation ballot
- Create a new draft and send it to a third sponsor recirculation ballot,
if necessary
- Forward the draft to RevCom for approval, if possible
- Process any interpretation requests received
March 2006
Task Group m met in
Denver, Colorado to complete processing the comments received from the
sponsor ballot that concluded after the November 2005 session. The task
group responded to all of the remaining comments The working group
approved the comment resolutions.
A sponsor recirculation ballot will begin shortly after the close of the
session.
The goals for the
May 2006 session are:
- Process the comments received from the sponsor recirculation ballot
- Create a new draft and send it to a second sponsor recirculation ballot
- Process any interpretation requests received
January 2006
Task Group m met in
beautiful Waikoloa, Hawai'i to process the comments received from the
sponsor ballot that concluded after the November 2005 session. Nearly
all of the technical comments were discussed and resolutions adopted.
Completion of the comment processing is expected in the March 2006 session,
with a sponsor recirculation ballot to follow shortly after the close of that
session.
The goals for the
March 2006 session are:
- Complete processing of the comments received on the sponsor ballot
- Send a draft to sponsor recirculation ballot
- Process any interpretation requests received
November 2005
Task Group m met in
Vancouver, B.C., Canada to process the comments received to date on the
sponsor ballot that was still in progress. A significant number of the
comments were discussed and resolutions proposed. No comment resolutions
were adopted, pending the closure of the sponsor ballot.
The goals for the
January 2006 session are:
- Process the comments received on the sponsor ballot
- Send a draft to sponsor recirculation ballot
- Process any interpretation requests received
September 2005
Task Group m met in
Garden Grove, CA to process the comments received with the
ballots on working group recirculation ballot 77. The comments received
on recirculation ballot 76 were dealt with in August at an authorized comment
resolution meeting.. The letter ballot passed,
with more than 96% approval.
The task group completed resolving all comments.
No changes were made to the draft (802.11REV-ma D4.0). At the meeting of
the 802 Executive Committee in July, conditional approval was granted to
forward 802.11REV-ma to sponsor ballot upon meeting the conditions described
in the LMSC Policies and Procedures. Theses conditions were met with the
passing of ballot 77 and were documented to the Executive Committee.
802.11REV-ma will now be sent for sponsor ballot, the next step toward
approval by the IEEE Standards Association as the new 802.11 standard.
The goals for the November 2005 session are:
- Process the comments received on the sponsor ballot
- Send a draft to sponsor recirculation ballot
- Process any interpretation requests received
July 2005
Task Group m met in
San Francisco, CA to process the comments received with the
ballots on working group recirculation ballot 75. The letter ballot passed,
with more than 93% approval..
The task group completed resolving all comments and directed the editor to
create a new draft, incorporating all comment resolutions. The new draft will be
constructed and sent for a working group recirculation ballot. This
recirculation ballot will conclude in time to receive the comments and process
them in a comment resolution meeting in August. Following resolution of
comments at the comment resolution meeting, a new draft will be created.
If necessary, this new draft will be sent to a second working group
recirculation ballot. If needed, a second comment resolution meeting
will be held and a subsequent draft created.
The task group also requested conditional approval to send the draft to
sponsor ballot, after completing all requirements in the LMSC Policies and
Procedures.
The goals for the September 2005 session are:
- Process the comments received on the recirculation ballot, if such is
necessary
- Send a draft to Sponsor Ballot, if it such a ballot has not already
begun
- Process any interpretation requests received
May 2005
Task Group m met in
Cairns, Queensland, Australia to process the comments received with the
ballots on working group letter ballot 74. The letter ballot passed,
with more than 90% approval..
The task group began processing the technical comments, completing proposed
resolutions to 89% of those technical comments. The remaining technical
comments will be addressed at an ad hoc meeting that will be announced
to occur during the week of either 20 June or 27 June 2005. Once all
comments, both technical and editorial, are addressed, the new draft will be
constructed and sent for a working group recirculation ballot. This
recirculation ballot will conclude in time to receive the comments and process
them at the July plenary session in San Francisco.
The goals for the July 2005 session are:
- Process the comments received on the recirculation ballot
- Create a new draft and issue it for a final recirculation ballot
- Process any interpretation requests received
March 2005
Task Group m met in
Atlanta, GA to continue the work of completing a revision of the 802.11
standard and its amendments, as well as to address an interpretation request.
The interpretation request was determined to be a request for consulting and
rejected.
The AP Functional Description group delivered their material to incorporate into the revision draft
for the first working group ballot. The task group accepted this
material and incorporated it into the draft.
The work on the draft of the 802.11 revision was completed and the draft
was forwarded to the working group for consideration via a letter ballot.
It is anticipated that this letter ballot will be completed prior to the May
session in Cairns, where the task group will take up the work of resolving the
comments received from the ballot.
The goals for the May 2005 session are:
- Process the comments received on the letter ballot
- Create a new draft and issue it for a recirculation ballot (this is a
stretch goal)
- Process any interpretation requests received
January 2005
Task Group m met in
Monterey, CA
to continue the work of completing a revision of the 802.11 standard and its
amendments, as well as to address an interpretation request. The
interpretation request, on the use of reserved bits in the Service field of
the PLCP header, was
examined and a response was generated. The interpretation response, as
approved by the 802.11 working group, is in document 05/1648r0. This
document can be obtained from the 802.11
interpretation
response page and also from the 802.11 document archive.
The AP Functional Description group also reported to the task group on
their progress toward having material to incorporate into the revision draft
for the first working group ballot.
The work on the draft of the 802.11 revision progressed well, leaving very
few work items that have been identified in previous
submissions to the 802.11 working group that have not yet been addressed. The work accomplished during this
session is consonant with the goal of the task group to send its draft to
working group letter ballot in March 2005.
November 2004
Task Group m met in San
Antonio
to continue the work of completing a revision of the 802.11 standard and its
amendments, as well as to address an interpretation request. The
interpretation request, on the accuracy of some material in Annex G, was
examined and a response was generated. The interpretation response, as
approved by the 802.11 working group, is in document 04/1454r0. This
document can be obtained from the 802.11
interpretation
response page and also from the 802.11 document archive.
The work on the draft of the 802.11 revision progressed well, with the
addressing a number of the work items that have been identified in previous
submissions to the 802.11 working group. The work accomplished during this
session is consonant with the goal of the task group to send its draft to
working group letter ballot in March 2005.
September 2004
Task Group m met in Berlin
to continue the work of completing a revision of the 802.11 standard and its
amendments. This work progressed well, with the adoption of submissions to
specify operation where regulatory agencies hold no sway and to address issues
with multirate operation introduced with 802.11g. The task group also
addressed a number of the work items that have been identified in previous
submissions to the 802.11 working group. The work accomplished during this
session is consonant with the goal of the task group to send its draft to
working group letter ballot in March 2005.
July 2004
Task Group M met in Portland and completed
many work items this week. Three submissions were received and adopted
for inclusion into the draft. The first submission dealt with a change
in terminology from "broadcast SSID" to "wildcard SSID" (04/759). The
second submission dealt with the definition of active scanning (04/795).
The third submission dealt with new requirements for both APs and stations
relating to the use of status and reason codes (04/698). The task group
is approximately half way through the work items that are tracked in 04/801.
The goals of TGm for the
Berlin meeting in September are to
address any interpretation requests received, consider any submissions made to
the task group, continue to work on the items listed in the issue tracking
document, and potentially, to adopt the first draft of the revision to the
standard in the task group.
May 2004
Task Group M met in Anaheim and completed
several work items this week. A submission on the definition and use of
a vendor-specific format for an information element was adopted. The
adopted content is available in document 04/522r1. Several items of work
from the issue tracking document (03/619r3) were completed, as well. As
a result, the task group directed the editor to produce a draft of the
revision of the standard, including 802.11-1999, 802.11a, 802.11b,
802.11b-Cor1, 802.11d, 802.11g, and 802.11h, as well as the items completed
during the meeting.
The goals of TGm for the Portland meeting in July are to
address any interpretation requests received, consider any submissions made to
the task group, continue to work on the items listed in the issue tracking
document, and potentially, to adopt the first draft of the revision to the
standard in the task group.
November 2003
Task Group M met in Albuquerque to
respond to the interpretation request received and to work on items to
correct editorial and technical issues in the standard. The
response to the interpretation request is available in document
03/875. The members of the task group began working on items
contained in document 03/619 .
The goals for the next meeting of Task Group m in Vancouver are to
respond to any interpretation requests received and to continue working
on the items listed in document 03/619."
July 2003
During the meeting held in San
Francisco, Task Group M considered one interpretation request and
submitted a response (document 03-576r1) to the working group.
The task group also continued to review the other documents that had
been submitted to the working group, regarding inconsistencies and
errors in the 802.11 standard and its approved amendments. The
task group has been accumulating work items in a tracking document
(document 03-619). At the September meeting in Singapore, the
task group intends to review and respond to any interpretation requests
received and resume its review of other documents that have been
submitted. The goal of the task group is to complete this review
of other documents and to determine a final list of work items.
If time permits, work will begin on the work items identified.
USEFUL LINKS TO OTHER SITES:
IEEE P802.11 WLANs RELATED
OTHER SITES
This page is maintained by Stuart
J. Kerry and Al Petrick .
Comments are welcome.
Copyright (c) 2008, the Institute of Electrical and Electronics Engineers,
Inc. (IEEE).
All rights reserved.
This website may contain names, logos, designs, titles, words, or phrases
that may
constitute trademarks, service marks, or tradenames of the IEEE or other
entities
which may be registered in certain jurisdictions.