IEEE
P802.11 - TASK GROUP M - MEETING
UPDATE:
Status of Project IEEE
802.11m
September
2009
Task Group m (TGm) met in
Waikoloa, Hawaii in September 2009.
1. LB149 status. TGm has approved comment resolutions for 518 comments received in LB149, and has 187 remaining comments to resolve.
Output documents:
Minutes - 11-09/1010r0
July
2009
Task Group m (TGm) met in
San Francisco, California in July 2009.
1. Adopted process for handling comments from LB149
2. Adopted process for deprecating features in IEEE Std 802.11
3. Addressed issues requiring editorial coordination with other 802.11 task groups
4. Approved resolutions for 13 comments received from LB149
Output documents:
Minutes - 11-09/0777r0
May
2009
Task Group m (TGm) met in
Montreal, Quebec in May 2009.
1. Initial letter ballot. TGm completed comment processing, produced an initial draft, and voted to send the initial revision draft to letter ballot.
2. Interpretation request. TGm processed one interpretation request regarding power saving functionality.
Output documents:
Minutes - 11-09/0564r0
Interpretation response - 11-09/0531r0
Mar
2009
Task Group m (TGm) met in
Vancouver, British Columbia in March 2009.
1. Officers. Adrian Stephens was elected as technical editor.
2. Plan of record. With a technical editor, a new plan of record was adopted. The first draft for letter ballot is expected in May 2009, with the completion of the project by March 2011.
3. Call for comments. Further processing of comments received in November 2008 continued.
Output documents:
Minutes - 11-09/0325r0
Current issues list - 11-08/1127r13
Jan
2009
Task Group m (TGm) met in
Los Angeles, California in January 2009.
1. Officers. There were no volunteers to serve as technical editor. As a result, TGmb revised its plan of record to state that no milestones are defined. The task group estimates that a revision will take approximately 24 months after the appointment of a technical editor.
2. One interpretation request on the sample frame encoding and FCS in Annex G was processed.
3. 45 additional comments from the call for comments were processed. In total 73 out of 104 comments have been processed.
Output documents:
Minutes - 11-09/0095r0
Interpretation response - 11-09/0042r0
Current issues list - 11-08/1127r12
Nov
2008
Task Group m (TGm) met in
Dallas, Texas in November 2008.
1. Officer election. Matthew Gast (Trapeze
Networks) was elected Chair, and Jon Rosdahl (CSR) was elected Secretary.
2. One interpretation request on DLS setup was processed.
3. Due to comments received on the PAR, a revised PAR was
approved for submission to the IEEE 802 EC.
4. The task group had requested input from the working group
on issues that should be addressed in the next revisions for the 802.11 standard.
The deadline for new inputs closed on November 10, with 104 comments received.
The group began processing received comments.
5. There was no change to the plan of record.
Output documents:
Minutes - 11-08/1363r0
Interpretation response - 11-08/1366r0
Current issues list - 11-08/1127r7
Sept
2008
- Task Group m (TGm) met in Waikaloa, HI,
at the Waikaloa Hilton Hotel. We had 2 time blocks.
- Some of the Task Group officers remain open -- Jon
Rosdahl (CSR) continues as Chair Pro Tem, and Mike Montemurro
(RIM) was
elected Vice Chair.
- A PAR Revision was created and approved for submission
for approval by 802 EC.
- Goals for Sept.
- Elect TG
Officers
- Process new interpretation requests
- Review Plan of Record and Timeline status
- Review and process work items for
maintenance/revision of the Standard
- Planning for Nov 2008 plenary session
1. Elect TG Officers: Mike Montemurro (RIM) was elected as Vice Chair
2. No Interpretation Requests were received
3. No change to Plan of Record
4. Issues were added to issues tracking document. Call for
Input reissued on Sept. 10, 2008.
- 5. Goals for Nov:
- o Missing
TG Officers Election/appointment
- o Process
new interpretation requests
- o Review
and process work items for
maintenance/revision of the Standard
- o Listen
to presentations on proposed changes to new
revision (Need to have 4-6 slot times)
- o Respond
to any EC comments on PAR modification.
- o
Planning for Jan 2009 Interim session
- Output Documents:
- 11-08-10375-00-000m-TGmb Agenda and Report Sept 2008
- 11-08-0917-01-000m-TGmb comment template
- 11-08-1114-00-000m-September 2008 interim meeting minutes
(Kona, Hawai'i)
- 11-08-1149-01-0000-Revision-Par-Proposal-802-11-2007
- 11-08-1127-02-000m-TGmb Issues List
July 2008
Task Group m (TGm) met in
Denver CO, at the Hyatt Regency Hotel. We had two time
blocks.
Three interpretation requests were processed.
The Timeline and plan of record was reviewed and a second call for
input was issued on Thursday, July 17, 2008.
- Goals for July 2008
- o Elect
TG Officers
- o
Process new interpretation requests
- o
Review and process work items for
maintenance/revision of the Standard
- o
Planning for Sept 2008 Interim session
- 3 Interpretation requests were processed:
- 1. Multiple BSSID and proper spacing
2. Section 7.3.1.17 -- Max SP Length subfield of the QoS Info
Field question
3. Section 7.3.2.20 -- Minimum PHY Rate field of the TSPEC IE
question
Goals for Sept.
- o Elect
TG Officers
- o Process
new interpretation requests
- o Review
Plan of Record and Timeline status
- o
Review and process work items for
maintenance/revision of the Standard
- o Planning
for Nov 2008 plenary session
- Output Docs:
- 11-08-0795-00-000m-Agenda and Reports
- 11-08-0872-03-000m-minutes July08
- 11-08-917 TGmb comment template
- 11-08-930-00-0000 3 responses to
Interpretation Requests July 2008
May 2008
- Task Group m met in Jacksonville, FL at the Hyatt Regency
Hotel. We had one time block and followed the Goals for May:
- Goals for May 2008
- Elect a TG
Chair/Secretary/Editor/Issue Tracker
- Process new interpretation requests
- Review and process
work items for maintenance/revision of the Standard
- Review and revise Timeline
- Planning for July 2008 plenary session
- 1. Officer Elections:
- Call for Nominations -- no nominations --
- Jon Rosdahl to be Chair Pro Tem
-
Nominations to be opened next session again.
- 2. Interpretation Requests:
- The Interpretation Request that was processed
was not officially possed to the IEEE, so we will wait on officially
processing
the request until it has been proper posted to the IEEE.
4. Created TGmb Plan of Record
- May 2008 – Issue Call
for Comment/Input
- July 2008
– begin process input and old
Interpretation requests
-
Acknowledge
previous Task Group referrals
- Sept 2008
– Start PAR Revision process
- Nov 2008 – close
receipt of new input
- Nov 2008 – WG/EC
approval of PAR Revision
- Dec 2008 –
NesCom/SASB approval PAR Revision
- Mar/May 2009 first
WG Letter ballot
- (includes All published Amendments as of
Mar/May 2009)
- July/Sept
2009 Recirc start
- Sept 2009 – Form
Sponsor Pool
- Nov 2009
– Sponsor Ballot Start
- (Include all published amendments as
of Nov
2009)
- Mar 2010
– Sponsor Recirc
- Nov 2010
– WG/EC Final Approval
- Mar 2011
– RevCom/SASB Approval
- CALL FOR
COMMENT/INPUT
- TGmb is requesting Comment/Input on the
802.11-2007 plus approved RevCom amendments.
- Input period is from May 2008 until Nov 2008.
- Presentations of proposed resolutions are
expected to be posted to IEEE Mentor server, and notification sent to
the 802.11m
listserv reflector.
- Notice was sent out on the 802.11 WG
Reflector on Tuesday, May 13, 2008
5. Goals for July
- Elect TG Officers
- TGmb
Chair
--- TGmb Secretary
- TGmb Editor
--- TGmb Comment Tracker
- Process new interpretation requests
- Review and process work items for
maintenance/revision of the Standard
- Planning for Sept 2008 plenary session
- Output Docs:
- 11-08-0588-02-000m-TGmb Agenda and Report May 2008
- 11-08-0622-00-000m-minutes-may-2008
March 2008
Task Group m (TGm) met in
Orlando at the Caribe-Royal Resort. The task group held one meeting and
focused on completing the response to a interpretation request Transmit
Power Control (TPC) in reference to EIRP in reference to P802.11-2007
Clause 7.3.2.18.
TBm completed and approved of the items in
the interpretation request and created doc: 08/0375r0 as the approved
response by the working group.
The relavent documents for this session were: 08/0390r0,
08/391r0, and 08/375r0.
Goals for May 2008
1) Process any new incoming interpretation requests
2)
Begin outlining requirements for the next revision of the P802.11
standard (including TGr, TGk, TGn) for target completion by 2011
January 2008
Task Group m (Tgm) did not meet
at the January interim session in Taipei, Taiwan. TGMb will resume
meeting at the March 2008 plenary session in Orlando, Florida. The
tentative goals for the group at the March 2008 session are as follows:
Goals for March 2008
1) Complete interpretation request on the subject of TPC
(transmit power control) in Clause 7.3.2.18
2) Process request on the usage of "shall" in Clause 10.0
3) Process any new interpretations requests from the IEEE
November 2007
Task Group m (Tgm) met in
Atlanta at the Hyatt Regency. The task group held one meeting and
focused on completing the response to a interpretation request on TCLAS
Element from 802.11e-2005 in doc: 07/2248r0. Tgmb completed and
approved of the items in the interpretation request and created doc:
07/2248r1.
The relavent documents for this session were: 07/2248r1,
07/2922r0, and 07/2920r0.
Goals for January 2008
1) Process interpretation request on the subject of TPC
(transmit power control) in Clause 7.3.2.18
September 2007
Task Group m (Tgm) did not meet
at the September interim session in Hawaii. TGMb will resume meeting at
the November 2007 plenary session in Atlanta, GA. The tentative goals
for the group at the November 2007 session are as follows:
Goals for November 2007
1) Complete interpretation response on TCLAS Element held
over from July 2007
2) Process interpretation request on the subject of TPC
(transmit power control) in Clause 7.3.2.18
3) Process request on the usage of "shall" in Clause 10.0
July 2007
Task Group m (Tgm) met in San
Francisco at the Hyatt Regency. The task group held two meetings and
focused on responding to a interpretation request on TCLAS Element from
802.11e-2005. Tgm complete 50% of the items in the interpretation
request. The relavent documents for this session were: 07/2248r0,
07-2151r0, and 07/2251.
Goals for September 2007
1) Complete interpretation response on TCLAS Element
May 2007
The task group finished its
work as TGma the January 2007 session. Task Group m (Tgm) met in
Montreal, Canada as TGmb. The task group held two meetings and focus on
gathering unresolved comments from the 802.11REV-ma sponsor ballot that
were considered "out-of-scope" of the standard. In addition the task
group started gathering interpretation requests that resolved around
channel numbering. The task group produced a document that combined the
comments and requests that will be resovled at the next 802.11 session
in July 2007.
Goals for July 2007
1) Begin work on resolving (out-of-scope) comments from
802.11REV-maD9.0
2) Resolve interpretation requests from January 2007
January 2007
Task Group m met in
London, UK. The task group considered a request for interpretation of
the standard on the subject of an indecipherable sentence in clause
17. The task group produced a response that was approved by
the 802.11 working group.
The task group also produced a proposal for a PAR for further
maintenance of the standard. This was also approved by the
working group and forwarded for the consideration of the 802 Executive
Committee.
Unless the consideration of the 802.11REV-ma draft by the
IEEE-SA Standards Board Review committee does not go well, this is the
last report of TGma, as it will be dissolved upon approval of that
draft by the IEEE-SA Standards Board.
November 2006
Task Group m met in
Dallas, TX. The result of the fourth sponsor recirculation ballot on
802.11REV-ma that concluded shortly before the November 2006 session
was successful, meeting the requirements of the LMSC Executive
Committee for conditional forwarding to RevCom. The editor
will produce a clean draft that accepts the marked changes.
The draft and the results of the sponsor balloting process will be
submitted to RevCom for their Early Consideration agenda that begins
after their meeting in December.
The task group also responded to one interpretation request
submitted on the subject of the replay protection mechanism used by the
TKIP cipher suite.
The goals for the January 2007 session are:
September 2006
Task Group m met in
Melbourne, Victoria, Australia to process the comments received from
the third sponsor recirculation ballot that concluded shortly before
the September 2006 session. The recirculation ballot resulted
in 41 comments to be addressed. The task group responded to
all of the comments. The working group approved the comment
resolutions. The editor was directed to produce an updated
draft. A third sponsor recirculation ballot will begin
shortly after the close of the session.
The task group also responded to two interpretation requests
submitted on the subjects of unknown values in a received information
element and conflict between clause 9 and annex C on the use of rery
counters.
The goals for the November 2006 session are:
-
•Process comments
received from fourth sponsor recirculation ballot, if necessary
-
•Submit
report to 802 EC for forwarding to RevCom
-
•Process
any interpretation requests received
July 2006
Task Group m met in San
Diego, California to process the comments received from the second
sponsor recirculation ballot that concluded immediately before the July
2006 session. The recirculation ballot resulted in 90
comments to be addressed. The task group responded to all of
the comments. The working group approved the comment
resolutions. A third sponsor recirculation ballot will begin
shortly after the close of the session.
The task group also responded to an interpretation request
submitted on the subject of RTS/CTS usage during interrupted fragment
bursts.
The goals for the September 2006 session are:
- Process the comments received from the third sponsor
recirculation ballot
- Create a new draft and send it to a fourth sponsor
recirculation ballot, if necessary
- Forward the draft to RevCom for approval, if possible
- Process any interpretation requests received
May 2006
Task Group m met in
Jacksonville, Florida to process the comments received from the first
sponsor recirculation ballot that concluded immediately before the May
2006 session. The recirculation ballot resulted in 156
comments to be addressed. The task group responded to all of
the comments. The working group approved the comment
resolutions. A second sponsor recirculation ballot will begin
shortly after the close of the session.
The goals for the July 2006 session are:
- Process the comments received from the second sponsor
recirculation ballot
- Create a new draft and send it to a third sponsor
recirculation ballot, if necessary
- Forward the draft to RevCom for approval, if possible
- Process any interpretation requests received
March 2006
Task Group m met in
Denver, Colorado to complete processing the comments received from the
sponsor ballot that concluded after the November 2005
session. The task group responded to all of the remaining
comments The working group approved the comment
resolutions. A sponsor recirculation ballot will begin
shortly after the close of the session.
The goals for the May 2006 session are:
- Process the comments received from the sponsor
recirculation ballot
- Create a new draft and send it to a second sponsor
recirculation ballot
- Process any interpretation requests received
January 2006
Task Group m met in
beautiful Waikoloa, Hawai'i to process the comments received from the
sponsor ballot that concluded after the November 2005
session. Nearly all of the technical comments were discussed
and resolutions adopted. Completion of the comment processing
is expected in the March 2006 session, with a sponsor recirculation
ballot to follow shortly after the close of that session.
The goals for the March 2006 session are:
- Complete processing of the comments received on the sponsor
ballot
- Send a draft to sponsor recirculation ballot
- Process any interpretation requests received
November 2005
Task Group m met in
Vancouver, B.C., Canada to process the comments received to date on the
sponsor ballot that was still in progress. A significant
number of the comments were discussed and resolutions
proposed. No comment resolutions were adopted, pending the
closure of the sponsor ballot.
The goals for the January 2006 session are:
- Process the comments received on the sponsor ballot
- Send a draft to sponsor recirculation ballot
- Process any interpretation requests received
September 2005
Task Group m met in Garden
Grove, CA to process the comments received with the ballots on working
group recirculation ballot 77. The comments received on
recirculation ballot 76 were dealt with in August at an authorized
comment resolution meeting.. The letter ballot passed, with
more than 96% approval.
The task group completed resolving all comments. No
changes were made to the draft (802.11REV-ma D4.0). At the
meeting of the 802 Executive Committee in July, conditional approval
was granted to forward 802.11REV-ma to sponsor ballot upon meeting the
conditions described in the LMSC Policies and Procedures.
Theses conditions were met with the passing of ballot 77 and were
documented to the Executive Committee. 802.11REV-ma will now
be sent for sponsor ballot, the next step toward approval by the IEEE
Standards Association as the new 802.11 standard.
The goals for the November 2005 session are:
- Process the comments received on the sponsor ballot
- Send a draft to sponsor recirculation ballot
- Process any interpretation requests received
July 2005
Task Group m met in San
Francisco, CA to process the comments received with the ballots on
working group recirculation ballot 75. The letter ballot
passed, with more than 93% approval..
The task group completed resolving all comments and directed
the editor to create a new draft, incorporating all comment
resolutions. The new draft will be constructed and sent for a
working group recirculation ballot. This recirculation ballot
will conclude in time to receive the comments and process them in a
comment resolution meeting in August. Following resolution of
comments at the comment resolution meeting, a new draft will be
created. If necessary, this new draft will be sent to a
second working group recirculation ballot. If needed, a
second comment resolution meeting will be held and a subsequent draft
created.
The task group also requested conditional approval to send the
draft to sponsor ballot, after completing all requirements in the LMSC
Policies and Procedures.
The goals for the September 2005 session are:
- Process the comments received on the recirculation ballot,
if such is necessary
- Send a draft to Sponsor Ballot, if it such a ballot has not
already begun
- Process any interpretation requests received
May 2005
Task Group m met in
Cairns, Queensland, Australia to process the comments received with the
ballots on working group letter ballot 74. The letter ballot
passed, with more than 90% approval..
The task group began processing the technical comments,
completing proposed resolutions to 89% of those technical
comments. The remaining technical comments will be addressed
at an ad hoc meeting that will be announced to
occur during the week of either 20 June or 27 June 2005. Once
all comments, both technical and editorial, are addressed, the new
draft will be constructed and sent for a working group recirculation
ballot. This recirculation ballot will conclude in time to
receive the comments and process them at the July plenary session in
San Francisco.
The goals for the July 2005 session are:
- Process the comments received on the recirculation ballot
- Create a new draft and issue it for a final recirculation
ballot
- Process any interpretation requests received
March 2005
Task Group m met in
Atlanta, GA to continue the work of completing a revision of the 802.11
standard and its amendments, as well as to address an interpretation
request. The interpretation request was determined to be a
request for consulting and rejected.
The AP Functional Description group delivered their material
to incorporate into the revision draft for the first working group
ballot. The task group accepted this material and
incorporated it into the draft.
The work on the draft of the 802.11 revision was completed and
the draft was forwarded to the working group for consideration via a
letter ballot. It is anticipated that this letter ballot will
be completed prior to the May session in Cairns, where the task group
will take up the work of resolving the comments received from the
ballot.
The goals for the May 2005 session are:
- Process the comments received on the letter ballot
- Create a new draft and issue it for a recirculation ballot
(this is a stretch goal)
- Process any interpretation requests received
January 2005
Task Group m met in
Monterey, CA to continue the work of completing a revision of the
802.11 standard and its amendments, as well as to address an
interpretation request. The interpretation request, on the
use of reserved bits in the Service field of the PLCP header, was
examined and a response was generated. The interpretation
response, as approved by the 802.11 working group, is in document
05/1648r0. This document can be obtained from the 802.11
interpretation
response page and also from the 802.11 document archive.
The AP Functional Description group also reported to the task
group on their progress toward having material to incorporate into the
revision draft for the first working group ballot.
The work on the draft of the 802.11 revision progressed well,
leaving very few work items that have been identified in previous
submissions to the 802.11 working group that have not yet been
addressed. The work accomplished during this session is consonant with
the goal of the task group to send its draft to working group letter
ballot in March 2005.
November 2004
Task Group m met in San
Antonio to continue the work of completing a revision of the 802.11
standard and its amendments, as well as to address an interpretation
request. The interpretation request, on the accuracy of some
material in Annex G, was examined and a response was
generated. The interpretation response, as approved by the
802.11 working group, is in document 04/1454r0. This document
can be obtained from the 802.11
interpretation
response page and also from the 802.11 document archive.
The work on the draft of the 802.11 revision progressed well,
with the addressing a number of the work items that have been
identified in previous submissions to the 802.11 working group. The
work accomplished during this session is consonant with the goal of the
task group to send its draft to working group letter ballot in March
2005.
September 2004
Task Group m met in Berlin
to continue the work of completing a revision of the 802.11 standard
and its amendments. This work progressed well, with the adoption of
submissions to specify operation where regulatory agencies hold no sway
and to address issues with multirate operation introduced with 802.11g.
The task group also addressed a number of the work items that have been
identified in previous submissions to the 802.11 working group. The
work accomplished during this session is consonant with the goal of the
task group to send its draft to working group letter ballot in March
2005.
July 2004
Task Group M met in
Portland and completed many work items this week. Three
submissions were received and adopted for inclusion into the
draft. The first submission dealt with a change in
terminology from "broadcast SSID" to "wildcard SSID"
(04/759). The second submission dealt with the definition of
active scanning (04/795). The third submission dealt with new
requirements for both APs and stations relating to the use of status
and reason codes (04/698). The task group is approximately
half way through the work items that are tracked in 04/801.
The goals of TGm for the Berlin meeting in September are to
address any interpretation requests received, consider any submissions
made to the task group, continue to work on the items listed in the
issue tracking document, and potentially, to adopt the first draft of
the revision to the standard in the task group.
May 2004
Task Group M met in
Anaheim and completed several work items this week. A
submission on the definition and use of a vendor-specific format for an
information element was adopted. The adopted content is
available in document 04/522r1. Several items of work from
the issue tracking document (03/619r3) were completed, as
well. As a result, the task group directed the editor to
produce a draft of the revision of the standard, including 802.11-1999,
802.11a, 802.11b, 802.11b-Cor1, 802.11d, 802.11g, and 802.11h, as well
as the items completed during the meeting.
The goals of TGm for the Portland meeting in July are to
address any interpretation requests received, consider any submissions
made to the task group, continue to work on the items listed in the
issue tracking document, and potentially, to adopt the first draft of
the revision to the standard in the task group.
November 2003
Task Group M met in
Albuquerque to
respond to the interpretation request received and to work on items to
correct editorial and technical issues in the standard. The
response to the interpretation request is available in document
03/875. The members of the task group began working on items
contained in document 03/619 .
The goals for the next meeting of Task Group m in Vancouver are to
respond to any interpretation requests received and to continue working
on the items listed in document 03/619."
July 2003
During the meeting held in
San
Francisco, Task Group M considered one interpretation request and
submitted a response (document 03-576r1) to the working
group.
The task group also continued to review the other documents that had
been submitted to the working group, regarding inconsistencies and
errors in the 802.11 standard and its approved amendments.
The
task group has been accumulating work items in a tracking document
(document 03-619). At the September meeting in Singapore, the
task group intends to review and respond to any interpretation requests
received and resume its review of other documents that have been
submitted. The goal of the task group is to complete this
review
of other documents and to determine a final list of work
items.
If time permits, work will begin on the work items identified.
USEFUL
LINKS TO OTHER SITES:
IEEE
P802.11 WLANs RELATED
OTHER SITES
This
page is maintained by Adrian
Stephens. and Matthew Gast
Comments are welcome.
Copyright (c) 2008, the Institute of Electrical and
Electronics Engineers,
Inc. (IEEE).
All rights reserved.
This website may contain names, logos, designs, titles,
words, or phrases
that may
constitute trademarks, service marks, or tradenames of the IEEE or
other
entities
which may be registered in certain jurisdictions.