Thread Links Date Links
Thread Prev Thread Next Thread Index Date Prev Date Next Date Index

RE: [10GBASE-T] Technical feasibility: power




Pat
Our first goal is to get to task force. Once we are in task force we can 
start to develop PHY proposals and evaluate them with power consumption 
being one of the criterion.

I think we over constrain the problem if we start to put numbers on the 
table while we are still in SG, and like many of our goals when do we 
pronounce success. If we have chosen 5 W for 1000BASE-T while still in SG 
in 1996, we did not have any parts that worked until after we finished the 
standard (my recollection is that they started to appear late 1999 and 
early 2000)and the first parts were over 5 Watts.

Bruce

At 11:31 AM 8/4/2003 -0600, pat_thaler@agilent.com wrote:

>Brad,
>
>A number of people have suggested that the benchmark be power estimated 
>for .09 um parts. Given where the technology seems to be going, that is 
>reasonable. So if someone chose to come out with a .13 um PHY at 6 W, I 
>wouldn't say we had failed.
>
>It will be an estimate like all the other objectives are at this point. If 
>new information comes to light, we may have to reconsider the objective as 
>we have for other objectives in the past. The ability to pass most of the 
>objectives is speculative at this point. This objective isn't any 
>different than the others. It might turn out that when we get near the end 
>of the project we discover that we can do 90 m but not 100 m (on 10BASE-2, 
>the distance had to be cut from 200 m to 185 m). We (802.3) would have to 
>decide whether the project was still viable with that objective change and 
>whether to go forward or to drop it.
>
>I agree with others including Bob Grow have said on feasibility - the 
>threshold of proof required to show feasibility goes up as the project 
>progresses. At this point, it is largely based on simulation and 
>theoretical calculation.
>
>Regards,
>Pat
>
>-----Original Message-----
>From: Booth, Bradley [mailto:bradley.booth@intel.com]
>Sent: Friday, August 01, 2003 12:54 PM
>To: stds-802-3-10gbt@ieee.org
>Subject: RE: [10GBASE-T] Technical feasibility: power
>
>
>
>Pat,
>
>I agree that power requirements and constraints in the use of Ethernet
>technologies have changed over the years.  I hope that the PHY vendors
>will provide estimations of the power requirements relative to selecting
>their proposal, and some have already given some rough power estimation
>numbers.  What if we select 5W as a number for the PHY to meet, but the
>first PHY in .13um is 6W?  Have we failed the objective?  If the next
>step in the process technology drops the power to 4W, can we consider
>that we met the objective with the first 6W PHY?  It's a tough number to
>target, and most of the numbers we're using are guestimates.  I think
>that the TASK FORCE (not the Study Group) should take into account the
>power when selecting proposals, but do we want to forego the standard
>development because we don't know the exact power requirement?  That's
>the question the study group needs to answer.  The feedback I get from
>customers is that they do want to see us move forward.
>
>Thanks,
>Brad
>
>-----Original Message-----
>From: pat_thaler@agilent.com [mailto:pat_thaler@agilent.com]
>Sent: Friday, August 01, 2003 12:45 PM
>To: Booth, Bradley; xichen@marvell.com; stds-802-3-10gbt@ieee.org
>Subject: RE: [10GBASE-T] Technical feasibility: power
>
>
>Brad,
>
>I'm pretty sure there wasn't an explicit power objective for GbE and
>10GbE though power was discussed in 1000BASE-T (I think mostly with
>regard to whether it would be low enough to make putting the thing in a
>chip feasible).
>
>Needs change with time. For 1000BASE-T initial use in end nodes, one
>just had to get it on a board with a gig MAC chip. I don't think there
>was any doubt that if the power allowed you to get it into a chip you
>could put it onto a board.
>
>The thing that is different is that the 10 Gig server market wants more
>than a MAC on the card. We are being asked to put TCP/IP Offload, RDMAP
>and iSCSI protocol, and in some cases IPSec on the card. These burn a
>lot of power too. That is why I think there should be a power objective
>when there hasn't been one in the past.
>
>Here's what I've gotten from the board specs:
>
>PCI Express -
>for a 4x or 8x card (this is the backplane bandwidth suitable for 10
>Gig), a standard height card is allowed 25 W, a low profile card is
>allowed 10 W. The 25 W number assumes that sufficient cooling is
>provided by the system.
>
>Infiniband -
>for a standard single wide slot is 25 W.
>
>Generally the systems vendors prefer that we stay under 15 W as a system
>full of 25 W cards is a lot for them to handle.
>
>If a 10GBASE-T transceiver was under 5 W or so, that would leave us
>power for the other functions we need on the PCI Express standard height
>card and on Inifiniband. That power level probably wouldn't enable low
>profile cards with full offload functions.
>
>Regards,
>Pat
>
>-----Original Message-----
>From: Booth, Bradley [mailto:bradley.booth@intel.com]
>Sent: Thursday, July 31, 2003 2:45 PM
>To: xichen@marvell.com; stds-802-3-10gbt@ieee.org
>Subject: Re: [10GBASE-T] Technical feasibility: power
>
>
>
>I was trying to recall if 802.3 used and specific power numbers in the
>GbE and 10GbE objectives or 5 criteria.  Considering I don't have web
>access right now, I'm just going by memory.  I believe 802.3 did not
>dictate power requirements, but did use power estimations in selection
>of the PHY to put into the draft.  This is just a Study Group, so it may
>only be required that to state that due consideration will be given to
>the power requirements.
>
>Thoughts?
>
>Thanks,
>Brad
>
>-----------------
>Sent from my BlackBerry.
>
>-----Original Message-----
>From: xichen@marvell.com <xichen@marvell.com>
>To: stds-802-3-10gbt@ieee.org <stds-802-3-10gbt@ieee.org>
>Sent: Thu Jul 31 13:52:04 2003
>Subject: RE: [10GBASE-T] Technical feasibility: power
>
>
>Burce,
>
>That is what I called painful lessons.  The customers always want parts
>that have high performance margin and low power.  I believe that has
>become the rule for our designers unless you really want something that
>can also fry eggs.  In order to give a reasonable estimation of the
>power comsuption, we should defintely take into account all possible
>technology and design tricks that we know and we can use in 5 years.  Of
>course, we cannot predict any magic stuff that can save the world will
>come out soon, but we can wait.
>
>A well-estimated number will save a lot words.
>
>Xiaopeng
>
>
>
>
>         Bruce Tolley <btolley@cisco.com>
>
>
>07/31/2003 12:56 PM
>
>         To:        xichen@marvell.com, Bruce Tolley <btolley@cisco.com>
>         cc:
>         Subject:        RE: [10GBASE-T] Technical feasibility: power
>
>
>
>
>Xiaopeng
>Thanks for the response
>
>The first 1000BASE-T parts were much more than a few watts. Also the
>power numbers on the roadmaps of the various vendors started dropping as
>soon one of the competitors achieved lower power numbers. All the
>sudden, the impossible became possible.
>
>And yes we need data to be presented in September.
>
>Bruce
>
>At 11:10 AM 7/31/2003 -0700, xichen@marvell.com wrote:
>
>Hi,
>
>I believe that everyone of us has painfully learned a lot from the
>history of 1000BASE-T.  We have observed the power of a single
>1000BASE-T dropped from a few watts to sub-watt level today.   And we
>can pretty confidently assess the impact of the technology that we are
>gonna use in 5 years and we definitely should take that into account
>NOW.
>
>Many circuit design experts will tell you that the power of digital
>circuit part can be scaled down while the semiconductor technology got
>significant improvement in the following years (how about using 65nm
>when 10GB-T reach the market), but the analog circuit part won't get too
>much benefit from that and its performance (for example, the ADC
>resolution) will be limited by some fundamental physical rule.  Due to
>the complexity increase of the DSP part and the analog part, even using
>65nm technology for digital circuit and using SiGe technology for analog
>circuit, to reach 100m on CAT-7, the estimated power of the transceiver
>(assume it is practically feasible) will be a number that can surprise
>you.  I believe more and more data will be given in the following
>meeting to show you the reality.
>
>Xiaopeng
>
>
>
>Bruce Tolley <btolley@cisco.com>
>Sent by: owner-stds-802-3-10gbt@majordomo.ieee.org
>
>07/31/2003 10:12 AM
>
>        To:        pat_thaler@agilent.com, yousefi@broadcom.com,
>pat_thaler@agilent.com, btolley@cisco.com, bradley.booth@intel.com,
>stds-802-3-10gbt@ieee.org
>        cc:
>        Subject:        RE: [10GBASE-T] September interim meeting
>
>
>Pat
>
>Thanks for providing detail on data centers. I would argue that in terms
>of broad market potential, 10GBASE-T would pass muster even if the only
>market application was data centers.
>
>On the power issue, the first 1000BASE-T implementations did not appear
>until well after the standard was done, some 5 years after the High
>Speed Study Group got its PAR, and consumed an obscene about of power.
>We might have never achieved the  low power 1000BASE-T PHYs we have
>today if we had tried to agree on exact numbers in 1996.
>
>Bruce
>
>At 11:00 AM 7/31/2003 -0600, pat_thaler@agilent.com wrote:
>Nariman,
>
>CX4 is useful especially when we have in rack connections to make or
>ones going to the next rack. However, the distance is too short for many
>other data center connects. Also, the cable for the long distance is
>relatively bulky which may be a problem for some uses. We will be glad
>to get it, but it only solves a corner of the problem space.
>
>Something for the longer distances in data centers that is lower cost
>than fiber would be useful. For that environment, it doesn't necessarily
>have to rely on already installed wiring. Running on existing wiring is
>nice, but not essential.
>
>My view of the important items for the data center environment:
>
>It must perform solidly on the media we choose for it - data integrity
>factors such as BER must be met.
>It must be able to live on "standard" server bus adapter formats with a
>TOE: e.g. PCI Express and Infiniband
>   which means power is a concern
>It must be transparent to existing MACs - that is, the MAC must see the
>same behavior it sees with 10 Gig fiber.
>100 m would be desireable (partly to enable future horizontal usage) but
>the data center could live with shaving something off that. (100 m is
>nice from a standards development standpoint as it saves us from arguing
>about what lower number is enough.)
>The media it runs over should not be so stiff or bulky that it is a
>problem to accomodate with normal rack and data center cable management.
>Of couse it must also meet EMI requirements
>
>Regards,
>Pat
>-----Original Message-----
>From: Nariman Yousefi [ <mailto:yousefi@broadcom.com>
>mailto:yousefi@broadcom.com]
>Sent: Wednesday, July 30, 2003 8:10 PM
>To: pat_thaler@agilent.com; btolley@cisco.com; bradley.booth@intel.com;
>stds-802-3-10gbt@ieee.org
>Subject: RE: [10GBASE-T] September interim meeting
>
>Pat,
>
>I agree that the issues you raised must be addressed by November. One of
>the biggest challenges for this group is to establish reality on
>technical feasibility on Cat7, Cat6 and Cat5e channels.  Different
>vendors have different conclusion on Technical feasibility. That is due
>to assumptions on alien cross talk mitigation techniques, impact on
>implementation impairments on SNR, channel model, coding gain, and
>analysis on chip complexity in a given process. Assumptions must be
>stated clearly by vendors that present technical feasibility. In this
>case, technical feasibility drives the broad market potential.
>Technical feasibility must be addressed at least based on the following
>criteria:
>
>1. Achievable distance on Class D channel with and without installation
>mitigation techniques.
>2. Achievable distance on Class E channel with and without installation
>mitigation techniques.
>3. Transceiver complexity in terms of estimated power dissipation and
>realistic targets for building blocks like ADC, PLL and etc 2-3 years
>from now.
>
>We reached a conclusion that cat7 cable or class F channel has high
>enough capacity for 10Gbps operation.  But, can a transceiver be built
>with reasonable power dissipation and cost say in 90nm process or finer
>geometries to achieve broad market potential?
>
>We need to keep in mind that customers have fiber and CX4 as
>alternatives.
>
>Nariman
>
>
>
>
>
>
>
>At 01:08 PM 7/30/2003 -0600, pat_thaler@agilent.com wrote:
>Bruce,
>
>Generally, when the group can agree on clear objectives, then they can
>finish the rest of the work. Fuzzy objectives often indicate a lack of
>real concensus.
>
>In November, I will also be expecting arguments that support the 5
>criteria based on the objectives -
>especially:
>Broad market potential - evidence that there will be a broad market the
>minimum requirements of the objectives are met.
>
>Technical feasibility - is it feasible to meet those minimum
>requirements
>
>Economic feasibility - when you have met the minimum requirements will
>cost be suitable to make it a viable product in the markets?
>
>In the discussions at the plenary, a power consumption issue was raised
>by some of the speakers.
>If the broad market potential is based in part on use in devices such as
>end nodes (including servers in data centers), then an objective for
>power consumption such that this can reside in server card formats would
>be important. Can it fit within the power constraints of a PCI Express
>board and an Infiniband board (remembering that one has to allow some
>power for the MAC and probably TOE/RDMAP engine)?
>
>Looking at the objectifves in agenda_1_07_03, I don't see any that
>address power consumption or the abilitiy to live on server card
>formats. In a quick search, I also didn't find any material on power
>consumption in the presentations that have been made to the study group.
>I hope that in September the group will address the issue of power.
>
>Regards,
>Pat
>-----Original Message-----
>From: Bruce Tolley [ <mailto:btolley@cisco.com>
>mailto:btolley@cisco.com]
>Sent: Monday, July 28, 2003 1:22 PM
>To: Booth, Bradley; stds-802-3-10gbt@ieee.org
>Subject: Re: [10GBASE-T] September interim meeting
>
>Brad:
>
>Thanks for the follow up.
>
>I am confident that if we can agree on crisp, clear objectives for 10
>Gbps reach and media supported in September that we can get our PAR
>approved and move into Task Force mode, which is where the real work
>begins.
>
>Bruce
>
>At 06:35 PM 7/24/2003 -0700, Booth, Bradley wrote:
>
>Study Group Members,
>
>Just to let others that were not at the meeting know the outcome of the
>802.3 Working Group meeting, the Study Group will have to complete its
>PAR, 5 Criteria and Objectives in November.  This gives the Study Group
>the task of completing the PAR, 5 Criteria and Objectives in 4 months.
>This will make our September Interim meeting extremely important.  We
>will need to complete the effort as much as possible to pre-submit to
>the 802.3 Working Group prior to the November Plenary.  November will
>permit us the ability to modify the PAR, 5 Criteria and Objectives prior
>to asking 802.3 to put the PAR on the NesCom agenda.  The September
>Interim meeting will focus on the completion of our PAR, 5 Criteria and
>Objectives.
>Thanks,
>Brad
>
>Chair, 10GBASE-T Study Group
>
>
>Bruce Tolley
>Senior Manager, Emerging Technologies
>Gigabit Systems Business Unit
>Cisco Systems
>170 West Tasman Drive
>MS SJ B2
>San Jose, CA 95134-1706
>internet: btolley@cisco.com
>ip phone: 408-526-4534
>"Don't put your hiking boots in the oven unless you plan on eating
>them."
>
>Colin Fletcher, The Complete Walker
>
>
>
>Nariman Yousefi
>Vice President Networking Engineering
>
>PH  (949) 585 5450
>FAX (949) 453 1848
>e-mail : Yousefi@Broadcom.com
>
>
>Bruce Tolley Senior Manager, Emerging Technologies Gigabit Systems
>Business Unit Cisco Systems 170 West Tasman Drive MS SJ B2 San Jose, CA
>95134-1706 internet: btolley@cisco.com ip phone: 408-526-4534
>"Don't put your hiking boots in the oven unless you plan on eating
>them."
>Colin Fletcher, The Complete Walker
>
>
>Bruce Tolley Senior Manager, Emerging Technologies Gigabit Systems
>Business Unit Cisco Systems 170 West Tasman Drive MS SJ B2 San Jose, CA
>95134-1706 internet: btolley@cisco.com ip phone: 408-526-4534
>"Don't put your hiking boots in the oven unless you plan on eating
>them."
>Colin Fletcher, The Complete Walker


Bruce Tolley
Senior Manager, Emerging Technologies
Gigabit Systems Business Unit
Cisco Systems
170 West Tasman Drive
MS SJ B2
San Jose, CA 95134-1706
internet: btolley@cisco.com
ip phone: 408-526-4534

"Don't put your hiking boots in the oven unless you plan on eating them."

Colin Fletcher, The Complete Walker