Phone Conference P1450.3 Working Group
Friday, Jan 17, 2003, 1:15 to 2:30pm PST
Attendees:
Tony Taylor
Daniel Fan
Discussion:
PAR entering the 4th year - The IEEE - PAR for this work will expire after one more year unless either: a) we request and extension, or b) we go to ballot. After a brief discussion as to the current status of our work, we decided not to request and extension at this time, as we fully expect to begin balloting this year.
Results of unofficial review - The review of Draft-D06 has been completed. Comments have been received from the following individuals listed below. Reviewer comments are available on the web site.
1/17 - Dan Fan / NP Test
1/31 - Dave Gallagher / Mentor
2/14 - Gregg Wilder / TI
2/28 - Bruce Kaufman / Teseda
3/14 - Don Organ / Inovus
Plans for reviewing and addressing the issues - We plan to review each reviewer list in these bi-weekly meetings. Reviewers will be invited to participate (and would, no doubt add value to the discussion) as we go over the issues. The tentative schedule for reviewing is identified in the list above. A new Draft-D07 will be created as the issues are addressed. A ResolutionDoc-D07 will capture the key issues and decisions.
DF - Review issues - We reviewed all the issues submitted by Dan. The discussion and resolution of the issues is included in the resolution doc (-D07).
Next meeting
Date: Friday, Jan 31, 2003
Time: 1:15 to 3:00 PDT
Phone Number: 1-800-486-2460
Participant: 324-637
Action Items:
Tony - send out an a thank-you letter to the D06 reviewers and invite them to participate in the review discussions.